c/o Barco House

Patterdale

Cumbria CA11 0NW

Home

CONTACT US

Website Made in Cumbria

All text and images © Patterdale Parish Community Flood Group 2017

Princes Countryside Fund

Please see below the latest recovery action plan from around the Parish. If you have any issues or updates to add please contact us.  Please note this just covers the “recovery” tasks. The work of the various future planning teams is covered in the Flood Action Plan. Last updated Tuesday 15th August  2017.

LATEST ACTION PLAN

Please see below the latest recovery action plan from around the Parish

#

Area

Issue

Current Status

Responsibility

Due Date

28

Hartsop

Howe Green Farm Repairs

NE/NT to provide update on farm payments for Robs Howe field.  Awaiting Feedback from NT

NT/NE

TBC

35

All

Beck monitoring

Depth boards arrived but need installing. Need cameras and depth/flow gauges in all key locations. All groups to confirm ideal monitoring techniques and get installed asap. Also working with Newcastle University on cameras

EA/CFG

September

39

Patterdale

Noran Bank Landslips

Work has been done to clear the field below the landslip and initial discussions have taken place between the landowners and Forestry on way to stabilise the bank. Forestry to provide an update - proposal with Noran Bank

Forestry

TBC

47

Glenridding

Beck Wall Benches

EA to supply benches and planters for Village Hall side of wall to replace wall seating

EA/CFG

September

5

Glenridding

Jenkins Field

Double yellow lines on road in place - need to sort flooding by slipway - suggestion for landscape of field to allow run off as originally proposed

EA/EDC

August

41

All

Gravel Management

Agree beck depths and ongoing permissions for gravel removal - Glenridding, Grisedale, Hartsop

EA/CFG

September

42

Grisedale

Clear Under Bridge

Working party to be arranged

CFG

September

43

Hartsop

Clear Under Bridge

Working party to be arranged

CFG

September

44

Deepdale

Lanefoot Drainage

Highways to sort road drainage by 1 Lanefoot

Highways

September

55

Deepdale

Clear Under Bridge

Working party to be arranged

CFG

September

46

Rookings

Clear beck behind rookings

Working party to be arranged

CFG

September

45

Glenridding

Clear Under Bridge

Working party to be arranged

CFG

September

53

Glenridding

Glenridding Flood Store

Repair Roof and sort electricity supply

CFG/LDNP

September

52

Glenridding

Beck Mouth by Glenridding Sailing Centre

Scheme for stabilising gravel at beck mouth - planting etc

EA/CFG

September

51

Gillside

Between Caravan Site and Greenside

EA/ERT/CFG wortking jointly on proposal for work to stabilise gravel above the caravan site

LDNP/CFG

September

54

Patterdale

Place Fell Landslips

Meet with Dalemain to discuss options for low level planting to stabilise fellside

Forestry/CFG

September

50

Grisedale

Drain at entrance to Grisdale Bridge

Road drain was tramaced over causing excess water to flow down Grisedale Bridge lane. Highways to investigate

Highways

September

48

Gillside

Campsite landslip and beck edge

LDNP to work with CFG on restore of landslip by campsite and beck edge below campsite including tree management

LDNP/CFG

September

26

Hartsop

Hartsop Road Hedge

Hedge by Hartsop Road End car park - Eric Wear has spoken to the Langton Centre people who've given permission for the hedge to be replace by a post/rail fence. Approval granted - work will be carried out by CFG - Note BT Cabinet. James to provide update based on discussion with Langton Centre

CFG

September

11

Glenridding

Trees on beck edge at Gillside

Need to talk to - Gillside about potentially doing some work on some of these

CFG

Autumn

13

Grisedale

Kennel Road trees

Trees near the pollarded oak still need addressing. Local quotes to be sought

CFG

Autumn

18

Patterdale

Goldrill Cottage Trees in Beck

Goldrill Cottage Trees in Beck - work already started will be finished off soon

CFG

Autumn

16

Patterdale

Place Fell Landslips

Place Fell Landslip Surveys - Awaiting outcome of survey - but separate survey was undertaken by Forestry - landslips due to Rock Bars on fell side - tree planting may alleviate future issues. Working with Forestry on this.

Forestry

Autumn

4

Glenridding

Recycling Centre

EDC repair work underway. Agreed with EA that CFG/EA will install a webcam/CCTV to monitor both the recycling centre and the beck by the village hall. Awaiting update from EA on cameras

EDC/EA/CFG/LDNP

End Dec

3

Glenridding

Beck Wall repair

Mayson Brothers Work progressing - Village Hall complete.  TIC Side work underway by Mayson Brothers - due for completion December 2017

EA

End Dec

Contact Us Completed Jobs Contact Us CFG Beck Work List Completed Jobs Complete Issues List Pilot Project Section 19 Report - Aug 2017

Section 19