Please see below the latest recovery action plan from around the Parish. If you have any issues or updates to add please contact us.  Please note this just covers the “recovery” tasks. The work of the various future planning teams is covered in the Flood Action Plan. Last updated Thursday 1st November 2018.

LATEST ACTION PLAN

Please see below the latest recovery action plan from around the Parish

#

Area

Issue

Current Status

Responsibility

Due Date

3

Glenridding

Beck Wall repair

Still need to complete monitoring centre by TIC and ramp below TIC. Reviewing work after heavy rain in November 2017 undermined part of the wall

EA

TBC

66

Rookings

Place Fell Bridge

Need to widen bridge to allow vehicle access. CFG to spec, LDNP to supply materials and CFG will do the work

CFG/LDNP

Dec-18

26

Hartsop

Hartsop Road Hedge

Hedge by Hartsop Road End car park - Eric Wear has spoken to the Langton Centre people who've given permission for the hedge to be replace by a post/rail fence. Approval granted - work will be carried out by CFG - Note BT Cabinet. James to provide update based on discussion with Langton Centre

CFG

Dec-18

35

All

Beck monitoring - Depth Boards

Install depth boards at Grisedale and Horsemans Bridge

EA/CFG

Nov-18

51

Gillside

Between Caravan Site and Greenside

EA/ERT/CFG wortking jointly on proposal for work to stabilise gravel above the caravan site

EA/CFG

Nov-18

58

Glenridding

Pollard Gillside Trees

Need to pollard those trees that became undermined in the 22nd November storm

EA/CFG

Nov-18

52

Glenridding

Beck Mouth by Glenridding Sailing Centre

Scheme for stabilising gravel at beck mouth - planting etc - could use silt from the Cubby work on Steamer Pier

EA/CFG

Dec-18

53

Glenridding

Glenridding Flood Store

Repair Roof and sort electricity supply. LDNP formal handover complete

CFG

Dec-18

59

Hartsop

Build up bank above Horsemans Bridge

Once again on 22nd November Hayeswater Gill burst and significant water flowed down to Hartsop Road End. Need to build up the bank and remove stone from the beck to prevent this

CFG/NT

Dec-18

42

Grisedale

Clear Under Bridge

Working party to be arranged

CFG

Mar-18

43

Hartsop

Clear Under Bridge

Working party to be arranged

CFG

Mar-19

55

Deepdale

Clear Under Bridge

Working party to be arranged

CFG

Mar-19

46

Rookings

Clear beck behind rookings

Working party to be arranged

CFG

Mar-19

28

Hartsop

Howe Green Farm Repairs

NT Tender underway to identify flood mitigation schemes for HoweGreen and Side Farm - Goldrill beck to be moved

NT/NE

Jul-19

13

Grisedale

Kennel Road trees & Drainage

CCC to review drainage and trees on Kennel road

CCC

Mar-19

Contact Us Completed Jobs Contact Us CFG Beck Work List Complete Issues List Completed Jobs Complete Issues List

CURRENT ACTION PLAN

See the latest recovery action plan including news on the Glenridding Beck Wall repairs and the latest updates on Jenkins Field as well as list of the jobs done so far

PHOTO GALLERY

See more photos from the floods of December 2015 and the recovery work that is still ongoing in Glenridding, Patterdale, Deepdale and Hartsop.

COMMUNITY FLOOD PLAN

Find out more about our Community Flood Plan, including our resilience planning and upstream beck management